Accra–Kumasi Expressway cash sits at Bank of Ghana as tenders drag on

Cost cut by US$1bn; savings to fund Accra Orbital Expressway

About US$3 billion to build the long-awaited Accra–Kumasi Expressway is sitting in an account at the Bank of Ghana. Construction on Ghana’s most important road has still not begun.

Finance Minister Dr Cassiel Ato Forson revealed the figure when he presented the 2027 Budget on behalf of President John Mahama. As of 11 November 2026, the project account held US$2.2 billion and GH¢9 billion, together about US$3 billion.

A cheaper road

The expressway will be a 198.7-kilometre, six-lane highway. Its engineers’ estimate is now US$2.98 billion, more than US$1 billion lower than the earlier estimate of about US$4 billion.

According to the Budget, the new figure covers construction, contingencies, supervision, land acquisition and compensation.

The government says the money comes without borrowing. The project is funded from petroleum revenue, through the Annual Budget Funding Amount (ABFA), together with mineral royalties set aside solely for the expressway.

International competitive tenders have been issued and are expected to close by the end of 2026. Each contract will need commitment-control approval and a value-for-money assessment before it is awarded.

Accra Orbital and a railway to the Sahel

The Budget says the US$1 billion saving will go to the Accra Orbital Expressway, a ring road meant to ease traffic in the capital.

The government also plans the Western Corridor Railway, from Takoradi Harbour through Nsuta and Awaso to the Nyinahin bauxite enclave. It would carry manganese and bauxite to a processing zone in the Western Region.

Ghana estimates about one billion tonnes of bauxite at Awaso and Nyinahin.

The railway will be paid for with petroleum revenue and mineral royalties in 2027 and 2028. “We will not borrow to build this railway,” Dr Forson said.

The line will later be extended to Hamile, on the border with Burkina Faso, with an inland port to serve the landlocked Sahel countries through Takoradi.

The questions

The promises are big, but they raise questions:

  • Why is US$3bn idle? Money sitting in an account doesn’t build roads. How much interest is it earning, and who is managing it?
  • How did the cost fall by US$1bn? Has the design changed, with fewer interchanges, a narrower scope or lower specifications? Or was the earlier estimate inflated? The Ministry of Roads and Highways should publish both estimates.
  • Who is bidding? The public deserves to know the shortlisted contractors and the evaluation criteria.
  • What does oil money lose? ABFA money spent on roads and railways can’t go to schools, hospitals or agriculture. Which projects will wait?
  • Will it be ready before 2028? Tenders close at the end of 2026, which leaves at most two years of construction before the next election. Will the road be finished, or only begun?

For millions of travellers, the Accra–Kumasi road is a daily danger. It is one of the country’s busiest and deadliest highways, choked with trucks carrying goods between the port and the north. A modern expressway would cut travel times, reduce accidents and lower the cost of moving goods.

Successive governments have promised it. With the money now in the bank, the test is whether this government will finally build it.

The Hawk has written to the Ministry of Roads and Highways requesting details of the tender process and the revised cost estimate. 

Share URL copied
Politics & Power

‘WAKE UP, JDM’S GOV’T IS COLLAPSING!’

A former member of the National Democratic Congress (NDC), Stephen Atubigah, has written an open letter to President John Dramani Mahama’s brothers,...

Politics & Power

‘OPONG-FOSU IS OUR MAN!’

• NDC movement throws weight behind Opong-Fosu for National Chairman The battle for the NDC National Chairmanship is gathering momentum after a powerful grassroots...

Mining & Energy

BUI POWER BLEW PAST BUDGET BY US$3.9M

The Bui Power Authority (BPA) spent US$3.93 million beyond its approved budget in 2025 without Board approval, while also paying more than GH¢202,000 in insurance premiums for five...